Policy Analysis · Energy ResilienceDraft for discussion · Revision 3

Siting Small Modular Reactors in Puerto Rico: A Two-Site Option at Aguirre and Ceiba

Siting, technology selection, grid integration, and extreme-event design considerations for approximately 1.1 GWe of firm nuclear capacity

Prepared byBenjamin John Schulz, independent researcher DateSeptember 24, 2026 StatusPlanning-level analysis; not an engineering, licensing, or cost estimate

Executive Summary

Puerto Rico's electric system combines aging fossil generation concentrated on the south coast, demand concentrated in the north, and transmission across the Cordillera Central that failed for extended periods after Hurricane Maria.[21] This paper assesses whether small modular reactors (SMRs) could provide firm, hurricane-resilient capacity. If so, it asks where they should be sited and which designs fit the island's grid.

The recommended configuration places two to three GE Vernova Hitachi BWRX-300 units at the site of the retiring Aguirre power complex in Salinas, and one six-module NuScale US460 plant on elevated land behind the former Naval Station Roosevelt Roads in Ceiba. Both sites would use seawater for cooling and place safety structures on raised ground set back from the coast. Net capacity would be 1,062 MWe, or 1,362 MWe with a third Aguirre unit. That is about 37 to 47 percent of the island's peak demand.

Key findings

  1. Aguirre is the strongest single site. Its 1,492 MW oil-fired complex is expected to retire around 2030, and the 500 MW AES coal plant nearby must close by 2032.[16][17][18] Reactors there would reuse an existing transmission hub, industrial land, and a nearby port. Their unit size (300 MWe) is below the 450 MW units the grid already accommodates at that node.
  2. Ceiba adds supply on the load side of the mountains. From Ceiba, power can reach the San Juan metropolitan area without crossing the Cordillera Central. NuScale's 77 MWe modules limit the size of any single trip on the weaker eastern grid. The vendor also states that a module can operate in island mode and support black start. That claim is unverified, but if confirmed it would materially aid post-storm restoration.[22]
  3. Seawater cooling removes the freshwater constraint. At Aguirre, a closed-cycle seawater system would withdraw roughly 3 to 4 percent of the approximately 654 million gallons per day the existing plant draws from Jobos Bay.[19]
  4. Passive safety addresses Puerto Rico's dominant hurricane failure mode. That failure mode is prolonged isolation: weeks without offsite power, road access, or resupply. Both designs remove decay heat without pumps, AC power, or operator action, according to vendor safety cases that licensing must confirm.
  5. The binding constraints are cost, grid stability, community acceptance, and Commonwealth policy. Comparable projects imply capital costs of at least $17 to $21 billion.[4][5] The Governor has stated she will not devote resources to evaluating nuclear power.[12] First power is unlikely before the mid-2030s.
Recommendation Fund a two-to-three-year site characterization program at Aguirre and Ceiba under an identified federal or private sponsor. It should cover coastal hazard, seismic, marine intake, population, and grid interconnection studies, plus structured engagement with Commonwealth agencies and host communities. Defer any construction commitment to the decision gates in Section 12.

1. Background

1.1 System conditions

1.2 Policy context

In June 2025, Governor Jenniffer González Colón stated that her administration is open to all generation technologies except nuclear and would not allocate time or resources to evaluating it.[12] She also signed the 2025 coal-plant extension, citing the need for "reliable, not intermittent" and affordable supply.[18] Separately, a former member of the Financial Oversight and Management Board has publicly proposed a federally led rebuild of the power system anchored in natural gas and nuclear energy.[12]

1.3 Prior nuclear work in Puerto Rico

Puerto Rico hosted the Boiling Nuclear Superheater (BONUS) experimental reactor at Rincón from 1964 to 1968. More recently, the Nuclear Alternative Project, a nonprofit led by Puerto Rican engineers, completed a DOE-funded preliminary feasibility study (2020). It then received a $1.6 million DOE award for a siting study that identified two candidate sites under NRC criteria (2021), and it published an economic study (2024).[13] The sites in this paper should be reconciled with that work.

2. Scope, Criteria, and Method

This is a planning-level screening analysis based on public sources. Candidate sites and technologies were evaluated against the following criteria:

  1. Resilience of supply to the principal load center after a major hurricane.
  2. Grid compatibility, meaning unit size relative to existing contingencies, access to existing transmission, and restoration role.
  3. Natural hazards: storm surge, tsunami, riverine and dam-break flooding, landslide, and seismic exposure.
  4. Cooling water availability and conflicts with public supply.
  5. Logistics for delivering large reactor components.
  6. Regulatory fit with NRC population and emergency-planning guidance, and the licensing maturity of each technology.
  7. Land, environmental, and community considerations.
  8. Indicative cost based on reference projects.

Assessments are qualitative except where noted. Water and cost figures are the author's calculations from stated assumptions (Appendix A). Vendor performance claims are identified as such.

3. Options Considered

Table 1. Comparison of configuration options

CriterionOption 1 (recommended): Aguirre + CeibaOption 2: Utuado + Ceiba (prior revision)Option 3: Aguirre onlyOption 4: No nuclear (current resource planning)
Net nuclear capacity1,062–1,362 MWe1,062–1,362 MWe600–900 MWe—
Post-hurricane supply to San JuanFirm supply on the load side (Ceiba)Firm supply on the load side (Ceiba)Still depends on cross-mountain linesDepends on transmission hardening and distributed storage
Use of existing grid assetsHigh (Aguirre hub)Low (new corridors from Utuado)HighModerate
Cooling-water conflictLow (seawater)High (Dos Bocas feeds public supply)LowNot applicable
Geotechnical and access riskModerateHigh (landslides, heavy haul)Low to moderateNot applicable
Technology riskTwo vendors; NuScale unbuiltTwo vendors; NuScale unbuiltOne vendor; under construction in CanadaEstablished technologies
Indicative capital cost≥ $17–21B≥ $17–21B≥ $7.6–11.3BPer the Energy Bureau's resource plan

Option 3 is a lower-cost first phase that is fully consistent with Option 1. It does not, however, address the north–south transmission vulnerability, which is the central resilience problem. Option 4 is the baseline against which any nuclear proposal would be evaluated in the Energy Bureau's resource planning process.

4. Recommended Configuration

Table 2. Recommended fleet

SiteTechnologyNet MWeRationale
Aguirre (Salinas)2 × BWRX-300; space reserved for a third unit600 (900)Replaces retiring fossil capacity at an existing hub. The unit size is below the existing 450 MW contingency at that node. It is the most mature SMR design in Western construction.
Ceiba (Roosevelt Roads)1 × NuScale US460 (6 × 77 MWe)462Firm supply on the load side. Small module trips suit the eastern grid. The vendor claims island-mode and black-start capability. The configuration matches the NRC-approved design.[2]
Total1,062 (1,362)Approximately 37% of peak demand (47% with the third Aguirre unit)

With seawater cooling, total size is limited by the grid, not by water. Additional units should follow only after grid studies confirm (a) sufficient fast reserves to cover the loss of an entire site and (b) acceptable operation during low-load hours (Section 8).

Schematic map of Puerto Rico showing the Aguirre and Ceiba sites, cross-island transmission, and screened-out sites Cordillera Central Cross-island transmission (extended outages after Maria) Load-side route; no Cordillera crossing El Yunque NF Jobos Bay NERR 2019–20 earthquake sequence (offshore) San Juan metropolitan area A A · Aguirre, Salinas BWRX-300 · 600–900 MWe B B · Ceiba NuScale US460 · 462 MWe Utuado Arecibo coastal plain Palo Seco Costa Sur Rincón (BONUS, 1964–68)
Figure 1. Recommended sites (filled) and screened-out sites (open). Schematic only. The coastline is approximate and positions are indicative. Author's illustration.

5. Site Assessments

5.1 Site A: Aguirre, Salinas

600–900 MWe2–3 × BWRX-300
1,492 MWRetiring fossil at site
25,789Salinas pop. (2020)[8]
~370 / mi²Salinas density

Description. The nuclear island would sit on elevated ground inland of the existing Aguirre complex, set back from the shoreline and the Jobos Bay mangroves. It would connect to the existing switchyard and transmission corridors, with seawater supplied by a protected intake and a buried pipeline.

Advantages

Constraints

5.2 Site B: Ceiba (Roosevelt Roads)

462 MWe6 × NuScale US460
11,307Ceiba pop. (2020)[8]
93%Navy land conveyed
Load sideOf Cordillera Central

Description. The plant would sit on elevated land behind the former Naval Station Roosevelt Roads, away from the waterfront. Seawater would be supplied from Ensenada Honda, and modules would be delivered by sea to the former base's deep-water pier.

Advantages

Constraints

6. Sites Screened Out

Table 3. Site screening matrix

CriterionAguirreCeibaUtuadoPalo Seco / San JuanArecibo plain
Surge and tsunamiModerateFavorableFavorableUnfavorableUnfavorable
Landslide and inland floodFavorableModerateUnfavorableModerateModerate
SeismicModerateModerateModerateModerateModerate
Cooling waterFavorableFavorableUnfavorableFavorableFavorable
Component deliveryFavorableFavorableUnfavorableFavorableFavorable
Grid positionFavorableFavorableModerateFavorableModerate
Population (NRC guidance)ModerateModerateModerateUnfavorableModerate
Land and competing useFavorableModerateModerateModerateModerate
Community and environmentModerateModerateModerateUnfavorableModerate

Ratings are qualitative screening judgments intended to scope site characterization. They are not study results.

7. Technology Assessment

Both selected designs are light-water reactors that use standard low-enriched uranium (<5 percent U-235). Their vendor safety cases state that decay heat is removed after shutdown without pumps, AC power, or operator action. The designs were assigned to sites by grid position rather than by preference for one vendor.

Table 4. Selected reactor technologies

AttributeBWRX-300 (Aguirre)NuScale US460 (Ceiba)
DesignNatural-circulation boiling water reactor (GE Vernova Hitachi)Integral pressurized water reactor; reactor, steam generators, and pressurizer in one vessel
Net output~300 MWe per unit77 MWe per module; 462 MWe for six
Passive decay-heat removal (vendor claim)Isolation condensers; at least 7 days without power or operator actionDecay-heat removal system and shared reactor pool; no AC/DC power, added water, or operator action for an indefinite period
Regulatory status (Sept 2026)Darlington Unit 1 under construction in Ontario.[5] NRC staff recommended issuance of the TVA Clinch River construction permit in June 2026.[6]NRC standard design approval issued May 29, 2025, for up to six modules.[2] No plant constructed.
Grid roleReplaces a larger existing contingency at an established nodeSmall contingency size; claimed island-mode and black-start capability[22]
AlternatesHoltec SMR-300; Westinghouse AP300 (neither yet licensed in the U.S.)2 × BWRX-300 if no NuScale plant is under construction by the procurement decision

7.1 Technologies not selected

8. Grid Integration

9. Extreme-Event Design Basis

Category 5 (sustained winds of 157 mph or greater) is a lower bound, not a design value. For new reactors, the NRC expects extreme-wind and wind-borne missile loads at very low annual exceedance frequencies (on the order of 10−7 per year). Puerto Rico is not covered by the mainland hazard maps in Regulatory Guide 1.221, so wind, missile, surge, tsunami, and flood parameters must be developed for each site and are expected to exceed nominal Category 5 values.

Experience suggests the governing hurricane risk is prolonged isolation rather than structural failure of containment. When Hurricane Andrew struck Turkey Point in 1992, safety-related structures performed as designed, although the site lost offsite power for several days and sustained significant non-nuclear damage. In Puerto Rico, the design must assume weeks without offsite power, road access, or resupply.

Table 5. Performance objectives for a Category 5 hurricane with a 30-day loss of offsite power

FunctionPerformance objective
Reactor core and spent fuelAutomatic shutdown and passive decay-heat removal. No fuel damage and no operator action required.
Safety-related structuresNo loss of function. No penetration by design-basis missiles. Interiors remain dry above the combined flood and tsunami elevation.
Cooling towers and seawater intakeLoss of fans or intake pumps is acceptable. Both are non-safety systems whose loss affects output only.
GenerationUnits trip on grid loss. Ceiba restarts in island mode if the capability is demonstrated; Aguirre resynchronizes as circuits return.
Public protectionEmergency planning zone sized under 10 CFR 50.160, potentially at the site boundary if supported by accident analysis.[7] Road access is not credited for cooling or protective actions.

9.1 Design requirements

10. Licensing Considerations

11. Cost, Financing, and Schedule

Table 6. Reference projects

ProjectCapacityEstimated costStatus
Carbon Free Power Project, Idaho (NuScale, 6 modules)462 MWe$9.3B including financing (2023); ~$20,100/kW[4]Cancelled November 2023
Darlington New Nuclear, Ontario (4 × BWRX-300)~1,200 MWeC$20.9B (~US$15.1B), 2024 dollars including interest; ~$12,600/kW[5]Unit 1 under construction

12. Implementation Pathway and Decision Gates

Table 7. Phased pathway

GateActivityDecision criterion to proceed
0Identify sponsor; fund site characterization at Aguirre and Ceiba; open consultation with host municipalities and agenciesSponsor and funding committed; Commonwealth agencies willing to participate
1Coastal hazard, seismic, liquefaction, marine intake, population, and interconnection studies; community-benefit frameworkBoth sites meet NRC population guidance; the Aguirre pad can clear the combined flood level; grid studies identify workable reserves
2Early Site Permit applications; preserve Aguirre switchyard and transmission rights through the fossil retirementsEarly Site Permits issued
3Aguirre Unit 1 construction permit application (Clinch River precedent)Financing closed; construction permit issued
4Ceiba technology confirmationA NuScale plant is under construction elsewhere; otherwise select the BWRX-300 alternate
5Aguirre Unit 2; optional Unit 3Operating experience from Unit 1; grid studies confirm reserves and low-load operation

13. Stakeholders and Governance

14. Key Uncertainties for Policymakers

  1. Which entity would sponsor and own the plants, and under what financing structure independent of PREPA's balance sheet?
  2. What conditions would secure Commonwealth consent, given the Governor's stated position?
  3. Do both sites satisfy NRC population guidance under the dose-based approach?
  4. What pad elevation and setback at Aguirre are required to clear the combined surge and tsunami hazard, and at what cost?
  5. On what terms, if any, would the Salinas and Guayama communities support nuclear replacement of coal and oil generation?
  6. Will NuScale's island-mode and black-start capability be demonstrated to a standard sufficient for inclusion in the island's restoration plan?
  7. What interim capacity bridges the 2030–2032 fossil retirements to nuclear operation?

15. Limitations

This analysis relies on public sources and planning-level approximations. It does not constitute an engineering design, cost estimate, site characterization, or licensing submission. Cost figures are scaled from reference projects. Water figures are thermodynamic approximations. Vendor performance claims, including passive-cooling duration and black-start capability, are unverified until confirmed through NRC review and testing. Nothing in this paper authorizes land acquisition, alters Act 17-2019 energy policy, or represents the position of any government entity.

Appendix A. Assumptions and Calculations

Table A-1. Estimated cooling-water requirements (closed-cycle seawater towers)

PlantHeat rejectedEvaporationSeawater withdrawalComparison
Aguirre, 2 × BWRX-300~1,140 MWt0.38 m³/s (~9 MGD)0.75 m³/s (~17 MGD)~3% of current Aguirre withdrawal (~654 MGD)
Aguirre, 3 × BWRX-300~1,710 MWt0.56 m³/s (~13 MGD)1.1 m³/s (~26 MGD)~4% of current withdrawal
Ceiba, 6 × NuScale~1,040 MWt0.34 m³/s (~8 MGD)0.68 m³/s (~16 MGD)No freshwater used for cooling

Appendix B. Acronyms

BWR
Boiling water reactor
CFPP
Carbon Free Power Project
DNER
Puerto Rico Department of Natural and Environmental Resources
DOE
U.S. Department of Energy
EPZ
Emergency planning zone
ESA
Endangered Species Act
FLEX
Diverse and flexible coping strategies (beyond-design-basis equipment)
HALEU
High-assay low-enriched uranium
MGD
Million gallons per day
MWe / MWt
Megawatts electric / thermal
NEPA
National Environmental Policy Act
NERR
National Estuarine Research Reserve
NRC
U.S. Nuclear Regulatory Commission
PREB
Puerto Rico Energy Bureau
PREPA
Puerto Rico Electric Power Authority
SMR
Small modular reactor

References

  1. U.S. Department of Energy / National Renewable Energy Laboratory. "Puerto Rico Energy Snapshot." https://docs.nlr.gov/docs/fy20osti/76607.pdf
  2. U.S. Nuclear Regulatory Commission. "NRC Approves Standard Design for NuScale US460 Small Modular Reactor." May 29, 2025. nrc.gov; Federal Register notice, June 4, 2025. federalregister.gov
  3. Utility Dive. "NRC approves NuScale's small modular reactor plant design." June 2, 2025. utilitydive.com
  4. National Rural Electric Cooperative Association. "NuScale and UAMPS End SMR Project (CFPP)." Business & Technology Advisory, December 2023. cooperative.com
  5. Nuclear Engineering International. "Ontario approves Darlington BWRX-300 SMR." May 2025. neimagazine.com; World Nuclear News. "Canada's first SMR project: How is CAD20.9 billion cost calculated?" June 2025. world-nuclear-news.org
  6. U.S. Nuclear Regulatory Commission. "Clinch River Nuclear Site Application." nrc.gov; American Nuclear Society. "Clinch River construction permit recommendation follows safety evaluation." July 1, 2026. ans.org
  7. 10 CFR 50.160, "Emergency preparedness for small modular reactors, non-light-water reactors, and non-power production or utilization facilities." ecfr.gov; Final rule, 88 Fed. Reg., November 16, 2023. federalregister.gov
  8. U.S. Census Bureau. QuickFacts: Salinas Municipio; Ceiba Municipio; Utuado Municipio. 2020 Census counts: Salinas 25,789; Ceiba 11,307; Utuado 28,287.
  9. U.S. Geological Survey. "Sedimentation Survey of Lago Dos Bocas, Puerto Rico, August 1994." WRI 95-4214. pubs.usgs.gov; Soler-López, L.R. "Sedimentation Survey of Lago Dos Bocas, Utuado, Puerto Rico, January 2010." SIM 3217. pubs.usgs.gov
  10. Bessette-Kirton, E., et al. "Landslides Triggered by Hurricane Maria: Assessment of an Extreme Event in Puerto Rico." GSA Today 29, no. 6 (2019). geosociety.org
  11. San Juan Daily Star. "US Navy transfers more land to Roosey Roads redevelopment authority." July 2026. sanjuandailystar.com; "Redevelopment of Roosevelt Roads lags." March 2026. sanjuandailystar.com; Local Redevelopment Authority for Roosevelt Roads. rooseveltroads.pr.gov; News is My Business. "Roosevelt Roads plans include spaceport, marina, golf course." March 2026. newsismybusiness.com
  12. San Juan Daily Star. "Governor: Nuclear plants won't be part of island's energy portfolio." June 30, 2025. sanjuandailystar.com; Centro de Periodismo Investigativo. "Puerto Rico Governor Bets on Trump's 'Energy Dominance' With Natural Gas." December 3, 2025. periodismoinvestigativo.com
  13. World Nuclear News. "SMRs economically feasible in Puerto Rico, study finds." February 8, 2024. world-nuclear-news.org
  14. El Nuevo Día. "Power demand rises as questions persist over Puerto Rico grid ahead of peak summer season." May 11, 2026. elnuevodia.com
  15. Institute for Energy Economics and Financial Analysis. "Rooftop solar in Puerto Rico reaches 10% as grid reliability continues to wane." ieefa.org
  16. Global Energy Monitor. "Aguirre power station." gem.wiki
  17. Grist. "As fossil fuel plants face retirement, a Puerto Rico community pushes for rooftop solar." grist.org
  18. Bloomberg Law. "Puerto Rico AES Coal-Fired Power Plant Wins Shutdown Reprieve." March 2025. news.bloomberglaw.com
  19. U.S. Environmental Protection Agency, Region 2. "Puerto Rico Electric Power Authority, Aguirre Power Plant Complex: NPDES Permit Fact Sheet." 2018. epa.gov
  20. National Oceanic and Atmospheric Administration. "Jobos Bay National Estuarine Research Reserve." coast.noaa.gov
  21. U.S. Energy Information Administration. "Puerto Rico's electricity service is slow to return after Hurricane Maria." Today in Energy. eia.gov
  22. NuScale Power. "Powering the 21st Century: Why the Power Grid Needs a Resilience Revolution." Vendor publication. nuscalepower.com
  23. Morgan Lewis. "NRC Altering Population Siting Guidance for Advanced Reactors." July 2022. morganlewis.com
  24. San Juan Daily Star. "Dredging begins in Las Mareas Bay in Guayama." July 2, 2026. sanjuandailystar.com
  25. U.S. Environmental Protection Agency. "EPA Settlement with AES Puerto Rico, L.P. Requires Action to Comply with Coal Ash Regulations." epa.gov

Additional sources consulted: 10 CFR Part 100 (reactor site criteria); NRC Regulatory Guide 1.221; USGS Puerto Rico–U.S. Virgin Islands seismic hazard model. Figures are planning estimates from public sources and do not represent licensed ratings for any Puerto Rico site. Suggested citation: Schulz, Benjamin John. Siting Small Modular Reactors in Puerto Rico: A Two-Site Option at Aguirre and Ceiba. Policy analysis, Revision 3, September 24, 2026.